Progress continues on the M74 Completion project with the successful erection of beams at Glasgow Road underbridge. The operation took place over two weekends in October and November using a crane to place the 39 precast concrete beams onto the structure. Placed end to end, the beams used to construct the bridge would fit down both sides of Rutherglen Main Street.Work was carried out in thre…..